2 marksProject Management
CAPE Management of Business Unit 2 · 2007 · Paper 2 · Question 2(d)(i)
Define the term 'Early Start Time' in relation to network diagrams.
The mark scheme is shown once you've answered.
Practise this questionDefine the term 'Early Start Time' in relation to network diagrams.
The mark scheme is shown once you've answered.
Practise this questionMore practice: the rest of this paper · more Project Management questions · all CAPE Management of Business Unit 2 past papers