Quelpr

CAPE Applied Mathematics Unit 2 · 2014 · Paper 2 · Question 2(a)(i)

An activity table shows activities A through H with their durations and preceding activities.

Using the algorithm method, or otherwise, construct the activity network for these activities.

This question uses a figure or table from the paper — you'll see it when you practise.

The mark scheme is shown once you've answered.

Practise this question

Other parts of this question

  1. 2(a)(ii)Copy and complete the table, giving the earliest start time, latest start time and float time for EACH activity.[4 marks]
  2. 2(a)(iii)Hence, obtain the critical path(s).[2 marks]
  3. 2(b)(i)Represent the circuit as a Boolean expression.[3 marks]
  4. 2(b)(ii)Construct its truth table.[4 marks]

More practice: the rest of this paper · more Graph Theory and Critical Path Analysis questions · all CAPE Applied Mathematics Unit 2 past papers