Quelpr

Other parts of this question

  1. 2(a)(i)Using the algorithm method, or otherwise, construct the activity network for these activities.[12 marks]
  2. 2(a)(ii)Copy and complete the table, giving the earliest start time, latest start time and float time for EACH activity.[4 marks]
  3. 2(a)(iii)Hence, obtain the critical path(s).[2 marks]
  4. 2(b)(i)Represent the circuit as a Boolean expression.[3 marks]

More practice: the rest of this paper · more Logic and Boolean Algebra questions · all CAPE Applied Mathematics Unit 2 past papers