CAPE Applied Mathematics Unit 2 · 2013 · Paper 2 · Question 2(a)(i)
An activity network where vertices represent activities and edges represent the duration in days. Unlimited workers are available.
Determine the EARLIEST start times of the activities S and X.
This question uses a figure or table from the paper — you'll see it when you practise.
The mark scheme is shown once you've answered.
Practise this question