CAPE Applied Mathematics Unit 2 · 2013 · Paper 2 · Question 2(a)(ii)

An activity network where vertices represent activities and edges represent the duration in days. Unlimited workers are available.

Determine the MINIMUM completion time of the project.

This question uses a figure or table from the paper — you'll see it when you practise.

The mark scheme is shown once you've answered.

Practise this question

Other parts of this question

  1. 2(a)(i)Determine the EARLIEST start times of the activities S and X.[3 marks]
  2. 2(a)(iii)Determine the LATEST start times of the activities X and Q.[3 marks]
  3. 2(a)(iv)Determine a critical path of the activity network.[2 marks]
  4. 2(a)(v)Determine the float time for activity T.[3 marks]
  5. 2(b)State the degree of the vertices A and C.[2 marks]
  6. 2(c)(i)Use the Hungarian algorithm to determine the supermarket to which EACH warehouse must be assigned in order to MINIMIZE the cost of delivery.[8 marks]
  7. 2(c)(ii)Hence, determine the total cost for EACH item at the four warehouses.[2 marks]

More practice: the rest of this paper · more Graph Theory and Critical Path Analysis questions · all CAPE Applied Mathematics Unit 2 past papers