CAPE Applied Mathematics Unit 2 · 2010 · Paper 2 · Question 2(d)(i)
An activity network diagram with activities A through G is shown.
Copy and complete the table for the earliest start time, latest start time, and float time for activities A through G.
This question uses a figure or table from the paper — you'll see it when you practise.
The mark scheme is shown once you've answered.
Practise this question