CAPE Accounting Unit 2 · 2012 · Paper 2 · Question 1(d)(iv)
Cal employs 30 persons with a normal working week of 40 hours. For 8 weeks in summer, overtime is paid at $2.50 per hour in addition to the normal piece rate. Summer weekly production: 20 000 luxury units and 24 000 standard units. Estimated labour time per sandwich: luxury 3.00 minutes, standard 2.00 minutes.
Calculate the additional pay for labour over the 8 weeks of the summer.
The mark scheme is shown once you've answered.
Practise this question