CAPE Applied Mathematics Unit 2 · 2011 · Paper 2 · Question 2(b)(ii)
Five activities, A, B, C, D and E, make up a project with given durations and precedence relations.
Copy and complete the table of Earliest Start Time, Latest Start Time, and Float for activities A to E.
This question uses a figure or table from the paper — you'll see it when you practise.
The mark scheme is shown once you've answered.
Practise this question